A load bank test runs your generator against an artificial electrical load at or near its rated output, which a no-load exercise cannot do. That matters most for diesel units. An engine that mostly runs lightly loaded can build up unburned fuel and carbon in its exhaust, a condition called wet stacking, and running it hot under load burns much of that off.
This guide is for facility managers and owners in Dallas, Fort Worth, Plano, Southlake and across North Texas. Texxas Power offers load bank testing on commercial standby systems, as described on our service and maintenance page.
What a load bank test is
A load bank is a device that puts a controlled, artificial load on a generator. Generac’s technical paper on the subject says the test simulates the designed usage of the generator at the rating on its nameplate and verifies that the primary components work under load. The paper adds that a normal exercise runs a generator below the load it can deliver, so a proper test must reach full output.
There are two kinds. A resistive load bank turns electrical output into heat and tests the engine to its design capacity. A reactive load bank adds apparent power and tests the alternator as well as the engine, which matters for sites that run motors. Generac’s paper describes the sequence like this:
- Connect the load bank at a dedicated breaker or spare bus connections.
- Run the generator with no load until the water temperature stabilizes.
- Add load in steps up to the target, recording engine and alternator readings at each step.
- Step the load down and let the unit cool as the manufacturer directs.
- Isolate the breaker, shut the generator down and remove the load bank.
What a stepped test looks like on the clock
The sequence below is an illustration for a 150 kW generator. The percentages and durations come from the NFPA 110 annual supplemental loading described later in this guide (2016 text, as reprinted in a December 2020 Cummins webinar). The kilowatt figures are simple arithmetic on the 150 kW rating.
| Stage | Load | Illustration: 150 kW set | Hold |
|---|---|---|---|
| 1. Warm-up | No load | 0 kW | Until the water temperature stabilizes (Generac) |
| 2. First step | 50% of nameplate | 75 kW | At least 30 minutes |
| 3. Second step | 75% of nameplate | 112.5 kW | At least 1 hour |
| 4. Full rating, where the test or specification calls for it | 100% of nameplate | 150 kW | As the manufacturer or specification sets |
Resistive or reactive: what each load bank proves
Most commercial generators are rated at a 0.8 power factor, so they cannot deliver their full kVA into a purely resistive load. Avtron Power, a load bank manufacturer, gives the example of a 500 kVA set that delivers only 400 kW into a resistive bank. That test loads the engine fully but loads the alternator to only about 80 percent of its rated current.
| Resistive load bank | Resistive plus reactive load bank | |
|---|---|---|
| Power factor of the test | 1.0 (unity) | 0.8, the usual nameplate rating |
| Engine | Tested to its full rated output | Tested to its full rated output |
| Alternator, voltage regulator, breakers, wiring | Not taken to their rated limit | Taken to rated current and heat |
| Illustration: 150 kW, 188 kVA set on 277/480 V (rated 226 A) | 150 kW is about 180 A | About 226 A at 150 kW plus roughly 113 kVAR |
The illustration uses the 226 A full-load current and 188 kVA rating in Generac’s published SD150 spec sheet (2021). The 113 kVAR is 188 kVA times 0.6. Avtron notes that consultants usually specify testing at the nameplate rating, and that ISO 8528 says a test report should flag any test run at a power factor different from the rated one. A resistive-only report is not wrong, but it answers a narrower question.
How to read a load bank test report
A report is only as useful as the readings on it. Generac lists what a load bank test can indicate: capacity to deliver the required power, voltage regulator response, voltage and frequency stability, control system behavior under load, and oil and fuel pressure.
| Reading | What it shows | What to question |
|---|---|---|
| kW at each step and at the top step | Whether the set delivers its rating | A top step below nameplate, or steps that were skipped |
| Power factor of the test | Whether the alternator was loaded to its rating | A resistive-only run presented as a full-rating proof |
| Voltage and frequency at each step | Regulator and governor holding steady under load | Drift or hunting as load rises, compared with the spec sheet for your model (the SD150 sheet lists steady-state regulation of plus or minus 0.25 percent) |
| Coolant temperature and oil pressure | Cooling and lubrication coping with sustained load | Values that keep climbing or falling instead of settling at each step |
| Exhaust temperature | Whether the engine is getting hot enough to burn off deposits | Low readings at high load, which are worth asking the technician about |
Ask for the readings, not only a pass or fail line.
How it differs from an exercise run or an outage simulation
Three different checks get called a test, and they prove different things.
| Check | What it proves | Load on the generator |
|---|---|---|
| Automatic exercise cycle | The engine starts and runs. It does not confirm the transfer switch operates or the system holds your building for hours. | Whatever the exercise uses, often little or none |
| Outage simulation (done on every Texxas Power service visit) | The system detects the loss, starts, transfers and carries your building’s actual load. | Your building’s real load on the day |
| Load bank test | The system carries its full rated load for a sustained period under controlled conditions. | Stepped up to rated output by the load bank |
If your building draws 40 percent of the generator’s rating on a normal day, the simulation proves it carries that. Only a load bank shows what happens at 100 percent.
What wet stacking is and how load testing addresses it
Diesel engines are built to run hot. Generac’s wet stacking fact sheet says an engine that is not asked for at least 30 percent of its rated output may struggle to reach its best operating temperature. Wet stacking is unburned diesel building up on the exhaust side, which can foul injectors and leave carbon on valves and in the turbocharger. The fact sheet says it happens most often when a generator runs consistently under 30 percent load, which is common when a unit is oversized for the building. One early sign can be oil dripping from the exhaust.
Kohler’s 2023 engineering paper adds that wet stacking does not damage an engine in the short term but can lead to poor performance and reduced engine life over time. Load banking works because it forces the engine to full-load heat and burns off the build-up. As Generac puts it, heat is the condition and load is the catalyst.
One caveat: engines have changed. Kohler’s paper argues that its KD series diesels can be exercised unloaded between annual load bank tests, while warning that aftertreatment and local air permits can set exercise requirements. Your manufacturer’s manual sets the right routine for your engine.
Wet stacking at a glance: symptoms, causes and fixes
| What the manufacturers say | |
|---|---|
| Symptoms | A dark, oily liquid that oozes from the turbocharger or drips from the exhaust outlet (Multiquip service bulletin, 2013; Generac). Over time, fouled injectors, carbon on valves and in the turbocharger, and lube oil contamination (Generac). |
| Causes | Running below roughly 30 percent of rated output for long periods, which Generac ties to an oversized or improperly sized generator; the Multiquip bulletin gives 40 percent as its threshold. Also a new engine placed straight into no-load or light-load duty, which may never break in properly (Multiquip). |
| Fixes | A few hours at about 75 percent of nameplate or more, raising exhaust temperature enough to vaporize the unburned fuel (Multiquip). In severe cases, load is raised gradually so heat and exhaust back pressure do not build too fast. |
| Safety | Exhaust temperature under load is above the ignition point of diesel and can reach 1,000 degrees F or more. The bulletin says such a unit should be load banked attended, with a fire extinguisher at hand and the exhaust inspected first. |
Illustration: a 150 kW generator serving a building that draws about 30 kW is running at 20 percent of its rating. The 30 percent line sits at 45 kW, so every exercise run at that building’s normal load stays below it.
What NFPA 110 says about load bank testing and exercise load
NFPA 110 is the standard for emergency and standby power systems. In the 2016 text, as reprinted in a December 2020 Cummins webinar, generator sets are exercised monthly for at least 30 minutes, either with loading that holds the manufacturer’s minimum exhaust gas temperature or at not less than 30 percent of nameplate kW. A diesel installation that cannot meet that is exercised monthly with available load, and annually with supplemental load: at least 50 percent of nameplate for 30 minutes, then at least 75 percent for one hour, 1.5 hours in total. Generac separately recommends at least two hours a year on a portable load bank for diesel systems.
Your jurisdiction may have adopted a different edition, and your authority having jurisdiction has the last word.
When a system should be load banked
- The system rarely runs under meaningful load, so a real outage would be its first proper test.
- A facility standard, insurer or authority asks for documented proof of capacity.
- The building has been added to since the system went in, and nobody has confirmed it still covers what is now connected.
- You have inherited a building with no service history for the unit.
- Major repairs are done, or the unit is about to enter NFPA 110 service.
Not every site needs one every year. If the generator already carries a meaningful share of its rating during each exercise and a recent outage simulation passed, the reason to load bank may be a standard or an insurer rather than the engine.
Which check fits which situation
| Situation | Check that fits | Why |
|---|---|---|
| Diesel that has mostly run lightly loaded | Load bank test, with the exhaust inspected first | Burns off deposits, but residual fuel and soot are a fire risk if the run is unattended |
| After major repairs or before entering NFPA 110 service | Load bank test | Generac recommends one in both cases |
| Motor-heavy site or alternator concern | Resistive plus reactive load bank | Loads the alternator and regulator to their rating, not just the engine |
What the visit involves
We bring a load bank to site and test the system to its rating, either as a standalone test or alongside a scheduled visit. Generac notes the method exercises the unit thoroughly without putting your critical loads in jeopardy. Tell us the brand and model number and we will tell you what the system needs. For the fuel side of reliability, read diesel fuel maintenance; for access at install, generator siting.
Quick answers
What is a load bank test?
A load bank test runs a generator against an artificial load at or near its nameplate rating while readings are recorded.
Is a load bank test the same as a monthly exercise run?
No. An exercise run proves the engine starts and runs, often at little or no load. A load bank test steps the generator up toward full rated output for a sustained period, under controlled conditions.
What is wet stacking?
Wet stacking is unburned diesel fuel and carbon building up on the exhaust side of an engine that runs too lightly loaded. Generac says it is most common below 30 percent load.
How long should a load bank test last?
Generac recommends at least two hours a year for diesel systems. The NFPA 110 text reprinted by Cummins sets a supplemental annual test of at least 1.5 hours for diesel installations that cannot meet the monthly loading. Your manual and authority set your number.
Do natural gas and propane generators need load bank testing?
Yes. Generac says gas generators need it too, because it burns deposits and moisture out of the engine and shows the unit delivers its rating.
Does Texxas Power offer load bank testing?
Yes. We bring in a load bank to prove a system at full rated output under sustained load, either as a standalone test or alongside a scheduled maintenance visit.
Does NFPA 110 require load bank testing?
Where a diesel installation cannot meet the monthly exercise loading, yes: the 2016 edition of NFPA 110, as reprinted in a December 2020 Cummins webinar, calls for annual supplemental load of at least 50 percent of nameplate for 30 minutes, then at least 75 percent for one hour. Your jurisdiction may have adopted a different edition, and your authority having jurisdiction has the last word.
What is the difference between a resistive and a reactive load bank?
A resistive load bank turns output into heat and loads the engine to its rating at a power factor of 1.0. A reactive load bank adds apparent power so the test runs at the usual 0.8 rating, which also loads the alternator and regulator to their limit.
How do you fix wet stacking?
Multiquip’s 2013 service bulletin describes the general cure as a few hours at about 75 percent of nameplate or more, which raises exhaust temperature enough to burn off the unburned fuel. A unit with a long light-load history should be tested attended, with the exhaust inspected first.
In this series: Diesel fuel maintenance · Paralleling vs a single generator · Generator vs UPS vs battery storage · Generator siting and clearances