How to size a commercial generator: load list, demand, motor starting and voltage

By Texxas Power

Free load analysis

We size to your building's measured demand before we recommend a unit. Free, and no obligation.

Request a site assessment →Or call (817) 439-9009. Emergency and after-hours rates apply.

A commercial generator is sized from measured demand, the hardest motor start and the building’s voltage, with room to grow, never from the building’s square footage, because floor area says little about what runs inside it.

This guide is for facility managers, owners and engineers in Fort Worth, Dallas, Plano, Southlake and across North Texas who want to understand a sizing proposal before they sign one. It explains the method. It is not a stamped design, and the final size comes from a load analysis of your building. Texxas Power does that analysis free.

1. Build the load list

Start by deciding what must keep running, then list every load on that circuit set. The Texxas Power commercial page describes the same starting point: actual demand across HVAC, refrigeration, life safety and process equipment, not an estimate from square footage. Generac’s engineering paper also separates essential from optional loads on new construction.

Load typeWhy it goes on the list
Life safety and egress lightingMust keep running when the grid is down
HVAC compressors and fansLarge motors with high starting current
Refrigeration and cold storageContinuous load that spoils stock if lost
Elevators and fire pumpsMotor loads with their own rules; elevators can push power back to the generator
Process equipment and pumpsSets how long and how hard the unit runs
IT, UPS and drivesNon-linear loads that add heat and distortion in the alternator

2. Demand versus connected load

Connected load is the sum of every nameplate. Demand is the most that actually runs at one time. A generator is sized to demand, so a measured figure beats a nameplate total.

For an existing building, the measurement is often already in your utility data. Oncor records the highest 15-minute demand in each billing month for non-residential customers, and customers with a standard advanced meter can pull 15-minute interval data from Smart Meter Texas, as Oncor describes. Generac’s sizing paper says peak load for existing buildings can be gathered from billing history, and unusual transients or harmonics can be seen with a power analyzer (Generac, Sizing Considerations for Commercial and Industrial Generators).

Two cautions. Take a full year of data so the summer cooling peak is in it. And the utility meter shows the whole building, while the generator may carry only the loads you chose, so the list from section 1 decides what counts.

3. Motor starting and step loading

Motor starting is a key factor in the size. A motor draws several times its running kVA for a moment, and the generator must supply it. Generac’s paper gives the example that a 100 hp NEMA code G motor needs about 600 starting kVA but only about 100 kVA to run.

Starting several motors together makes it worse. Generac’s example: three 100 hp motors started at once would take two 300 kW units about 600 kW to start, and starting them one after another cuts the starting kW required by 40 percent. Stepping the loads on in sequence is a design choice, and it can let a smaller generator do the job.

Start orderMotor startingLoad on the generator at that moment
Motor 1100 hp, NEMA code GAbout 200 kW
Motor 2Second 100 hp motor startsAbout 285 kW (motor 1 running plus motor 2 starting)
Motor 3Third 100 hp motor startsAbout 370 kW

Voltage dip is the other limit. Generac says most NEMA motors withstand a dip of up to 30 percent, while general facility loads can reset beyond 15 percent. Reduced-voltage and soft starters, and variable frequency drives, lower the starting demand. Kohler’s engineering paper notes that a 30 percent voltage dip reduces starting kVA by about 50 percent, but it also reduces the torque a motor can deliver (Kohler, Sizing Generators for Motor Starting).

How much starting kVA does a motor need?

The motor nameplate carries a NEMA code letter, and each letter stands for a range of locked-rotor kVA per horsepower. Multiply the range by the horsepower to get the starting kVA.

NEMA code letterStarting kVA per hp
A0 to 3.14
B3.15 to 3.54
C3.55 to 3.99
D4.0 to 4.49
E4.5 to 4.99
F5.0 to 5.59
G5.6 to 6.29
H6.3 to 7.0
J7.1 to 7.99
K8.0 to 8.99
L9.0 to 9.99
M10.0 to 11.1
N11.2 to 12.49
P to V12.5 to 22.4 and up

Source: NEMA code letters as tabulated in Kohler’s motor starting paper and Generac’s sizing paper, which excludes IEC motors, specialty motors and submersible pumps. Kohler’s example: a 50 hp code F motor needs about 280 starting kVA (50 x 5.59). Small motors carry higher letters; Kohler lists code G for 15 hp and up.

How does the starter type change the demand?

The starter between the panel and the motor changes how hard the start hits the generator. Kohler describes these effects.

StarterEffect on the generator
Across the line (full voltage)Starting current is typically six times full-load current until the motor reaches about 75 percent of rated speed
Part windingMaximum inrush is reduced to 60 to 70 percent of normal
AutotransformerTaps give 80, 65 or 50 percent of line voltage (64, 42 or 25 percent of full torque); use the 80 or 65 percent taps
Wye-deltaStarting current and torque fall to 33 percent of the delta values
Solid-state (soft start)Ramps voltage at a set rate; field settings change the result, and it can distort voltage

Kohler adds that only closed-transition reduced-voltage starters help on generator power, because an open-transition starter creates a spike in kVA demand when it switches between steps.

How much voltage dip is acceptable?

FigureWhat it meansSource
15 percentGeneral facility loads beyond this can resetGenerac
20 percentLimit many specifying engineers prefer, so motor contacts hold in; some relays and contactors chatter at this levelKohler
30 percentMost NEMA motors withstand a dip up to thisGenerac
30 to 35 percentTypical motors sustain this instantaneous dip before the starting contacts drop outKohler

A generator already carrying 50 percent load may dip about 2 percent more than its published figure (Kohler).

A worked illustration: from load list to a first-pass size

This illustration uses a made-up clinic and Generac’s rules of thumb for NEMA code G motors: about 2 kW of engine power to start each horsepower and about 0.85 kW to run it. It is not a Texxas Power project or a stamped design.

Load on the emergency panelRunning demandStarting demand
Life safety, egress lighting, fire alarm8 kWNone
IT and controls22 kWNone
Refrigeration10 kWNone
Water pump, 20 hp17 kW (20 x 0.85)40 kW (20 x 2)
HVAC units 1, 2 and 3, 20 hp each17 kW each, 51 kW together40 kW each
Total running108 kW

With step loading, the 40 kW of lighting, IT and refrigeration goes on first, then each motor starts in turn.

StepWhat startsAlready runningStarting kWEngine kW at that moment
1Lighting, IT, refrigeration0 kW40 kW (steady)40 kW
2Water pump40 kW40 kW80 kW
3HVAC unit 157 kW40 kW97 kW
4HVAC unit 274 kW40 kW114 kW
5HVAC unit 391 kW40 kW131 kW

The worst moment is step 5 at about 131 kW. Starting all four motors at once would ask for 40 + (80 hp x 2) = 200 kW, so sequencing cuts the peak by about a third. The running load of 108 kW is about 135 kVA at the 0.8 power factor that Kohler says three-phase sets are rated at (108 / 0.8).

That is only the first screen. A real selection then checks voltage dip and frequency dip for a specific model, and Kohler notes that different manufacturers’ sizing software can give quite different results. The growth allowance from section 4 comes after. A proposal should show the step table, not just a number.

What about electronic, regenerative and UPS loads?

LoadConcernWhat Generac says to do
Rectifiers, VFDs, UPS (include battery recharge load)Non-linear current distorts voltage; harmonic currents use alternator capacity and add heatKeep voltage distortion within the limit your engineer sets (Generac cites IEEE 519); use filters, or upsize the alternator or add other load
Elevators and cranesThey send power back to the generator, which can cause a shutdownAdd an offsetting load such as building load, a brake resistor or a load bank
Lightly loaded UPS, HID lighting, power factor correction capacitorsLeading power factor can cause voltage instability or over-voltage trips; generators handle 0.8 lagging to unityOffset with lagging loads, or switch loads off while on generator power

4. Reserve and growth

Leave room for loads you will add. There is no universal percentage: the allowance depends on your plans, so settle it at the load analysis. Paralleled units are one way to add capacity after day one, and larger systems, including paralleled and N+1 configurations, are engineered and quoted individually.

Bigger is not automatically safer. A unit that runs far below its rating wastes fuel and can suffer from wet stacking, covered in the load bank testing guide. If a smaller system covers your load, Texxas Power says so.

5. Voltage and phase

The generator’s voltage and phase must match the building’s service and the transfer switch. Confirm it from the panel schedule before anything is ordered.

Voltage and phaseTypical useNote
120/240 V single-phaseSmall commercial buildingsOffered on smaller commercial sizes
120/208 V three-phase (208Y/120)Offices, retail and multi-tenant buildings served at 208 voltsGenerac lists it as option G on liquid-cooled automatic standby units
120/240 V three-phaseBuildings served at 240 volts three-phaseGenerac option J; confirm the winding on the spec sheet
277/480 V three-phase (480Y/277)Larger commercial and light industrial buildingsGenerac option K; not every option exists at every size

Source: Generac support, phases and voltage options for liquid-cooled automatic standby generators.

6. How fuel type changes the rating

The same engine can produce less on one fuel than another. Generac’s own example is a 26 kW air-cooled unit rated at 26,000 watts on propane and 22,500 watts on natural gas (Generac support, home standby). Commercial spec sheets carry their own fuel columns, so read the rating for the fuel you will use. The same article, which covers air-cooled home standby units, gives about 1 percent less power per 10 degrees Fahrenheit above 60, which matters in a North Texas summer.

7. Where Texxas Power starts

The commercial page lists sizing bands for small offices and clinics, multi-tenant buildings and light industrial sites, with standard systems from 22 to 150 kW. Every project begins with a free load analysis, and the proposal carries the reasoning in it. Ask for the free load analysis, or call (817) 439-9009 or (972) 944-5520.

In this series: project timeline · remote monitoring · paralleling vs a single generator

Quick answers

How do you size a commercial backup generator?

From measured demand plus the hardest motor start, at the building’s voltage, with room to grow. Texxas Power starts with a free load analysis and puts the reasoning in a written proposal.

Can you size a commercial generator by square footage?

No. Floor area says little about the load inside a building, so Texxas Power sizes to real demand instead.

What is the difference between connected load and demand?

Connected load is every nameplate added together. Demand is the most that runs at once, and the generator is sized to demand.

How do I find my building’s peak demand?

Use your utility data. Oncor records the highest 15-minute demand each month for non-residential customers, and interval data is available through Smart Meter Texas for standard advanced meters.

Why do motors matter so much?

Starting current is several times running current. Generac’s example is a 100 hp motor needing about 600 starting kVA against about 100 kVA to run.

What voltage does a commercial generator need?

The same as the building’s service, commonly 208Y/120 or 480Y/277 three-phase. Not every voltage is offered at every size.

What does the NEMA code letter on a motor mean?

It gives the motor’s starting kVA per horsepower. Code G, common on motors of 15 hp and up, is 5.6 to 6.29 kVA per hp, so a 20 hp code G motor needs roughly 112 to 126 kVA to start.

How much voltage dip can a generator have when starting motors?

Most NEMA motors withstand up to 30 percent, but general facility loads can reset beyond 15 percent and many engineers specify 20 percent or less. The limit comes from the most sensitive load on the circuit.

Does fuel type change the generator’s rating?

Yes. In Generac’s home standby example the same 26 kW air-cooled unit makes 26,000 watts on propane and 22,500 on natural gas.

Texxas Power Home Services LLC holds Texas Electrical Contractor License #41809 and has a 5.0 rating across 200+ Google reviews.

Is there a commercial generator sizing calculator?

A generic online calculator gives a starting number at best. Commercial sizing depends on your measured demand, motor starting and voltage, so Texxas Power starts with a free load analysis and puts the reasoning in the written proposal. The load list in section 1 shows the information any calculator would need.

Free site assessment

Planning Standby Power for Your Building?

Tell us what has to stay running. We walk the site, review your panel schedule and demand history, and give you a written proposal with the reasoning in it.

  • Call
  • Emergency
    24/7 phone line, emergency and after-hours rates apply
  • Offices
    13013 Harmon Rd, Suite 1305, Fort Worth, TX 76177
    3400 Carlisle St., Suite 320, Dallas, TX 75204
    8105 Rasor Blvd., Suite 218, Plano, TX 75024